Sector | transportation- roads& highways, railways |
Funding Agency | GoN |
Project Location | Rukum West |
Province | Karnali |
Project Started Date | 1 January 2015 |
Project Completion Date | 1 November 2016 |
Project Status | Completed Projects |
Clients | Puspalal (Mid Hill) Highway Project, Western Sector, Department of Roads |
Detailed Engineering Survey, Design, Preparation of Detailed Project Report (DPR) was carried out for the Project Road for Hasibang-Chaurajahari section of Pushpalal (Mid-Hill) Highway Project for upgrading to Black Top Standard having length of 33.18 Km. The objectives of the project is to carry out review of existing road and its corridor, detailed engineering survey and design of highway including pavement design and other structures, preparation of contract packages document and preparation of detailed project report (DPR) of mentioned road sections. Total Project Cost NRs. 1,570 million