Sector | transportation- roads& highways, railways |
Funding Agency | GoN |
Project Location | Bhaktapur, Kavrepalanchok |
Province | Bagmati |
Project Started Date | 4/1/2023 |
Project Completion Date | 1/1/2024 |
Project Status | Completed Projects |
Clients | Quality Research and Development Centre, Department of Roads |
The Thathali-Rabiopi Road Tunnel lies in Bhaktapurr district. The Thathali Rabiopi Road Tunnel effects directly and indirectly positive influence on Bhaktapur, Nuwakot, Sindhupalchowk and Kathmandu districts. The construction of tunnel helps to develop the city at Panchkhal area and whih may be useful in reducing densely populated Kathmandu Valley population to Panchkhal area. It also helps to reduce connectivity distance of Arniko highway to reach China border, Kodari. The construction of road tunnel reduces the tentative length of the road upto 17 Km and hence reduces the travel time making the travel safe in geographically steep terrain and enhance the economic growth in these areas.
The main objective of the consulting services is to conduct the feasibility study of road tunnel to be constructed under DB or EPC Contact Model. The Feasibility study was conducted for 2 Tunnels as follows with Access Road length of 1783 m.
S. N
Description
Tunnel-1
Tunnel-2
•
Tunnel shape
Modified-Horse Shoe
Modified-Horse Shoe
•
Tunnel size
11.3 m* 7.44 m
11.3 m* 7.44 m
•
Tunnel length
2360 m
2220 m
•
Tunnel Width
Double Lane Single Tube
Double Lane Single Tube
•
Excavation method
Conventional Drill and blast
Conventional Drill and blast
•
Construction approach
NATM
NATM
•
Carriage way width
9.5 m
9.5 m
•
Escape Tunnel
Single Lane parallel to main tunnel
Single Lane parallel to main tunnel
•
Escape Tunnel Size
4.22 m x 4.00 m, Inverted D-Shape with cross passage @375m interval
4.22 m x 4.00 m, Inverted D-Shape with cross passage @375m interval
•
Pavement type
Reinforced Concrete
Reinforced Concrete