Sector | water resources/irrigation, natural resources, agriculture & food security |
Funding Agency | GoN |
Project Location | Sindhuli |
Province | Bagmati |
Project Started Date | July 2012 |
Project Completion Date | June 2013 |
Project Status | Completed Projects |
Clients | Department of Irrigation |
The main objective of this study is to carry out pre-feasibility level study to identify various components of the diversion projects with irrigation and hydropower as the major water users; and as such a decision is made to decide for further study based on it’s economical, financial, and environmental considerations. Installed Capacity of the Hydropower Component of the project is 36 MW and Irrigated command area of Bagmati irrigation project is 122,000 ha. The project cost is NPR 35,685.5 million.