Sector | urban development, architecture and other infrastructure |
Funding Agency | GoN |
Project Location | Dang |
Province | Lumbini |
Project Started Date | 7/5/2022 |
Project Completion Date | 4/4/2023 |
Project Status | Completed Projects |
Clients | Provincial Government, Lumbini Province, Provincial Infrastructure Development Authority, Rapti Valley, Dang, Nepal |
Under preparation of detailed project report of Lumbini Provincial Capital City; prefeasibility study of Highway Tunnel connecting Lumbini Provincial Capital City and Dang Valley, preparation of DPR of River Training works along Rapti River, preparation of DPR of Main Road of Administrative Zone, preparation of DPR of Bus Park, preparation of DPR of Auto Village and preparation of DPR of Administrative as well as Residence buildings with facilities.
• Prefeasibility Study of Highway Tunnel connecting Lumbini Provincial Capital City, Kapilvastu and Dang Valley
Section I: Tarai-Dang Road Tunnel
Number of Alignments Considered for Study: 3 Alignments
Length of Feasible Alignment: 4.5 Km (Bankas Basa-Rangsing Khola)
Preliminary Construction Cost: NRs. 21.56 billion (163.03 million US$)
Section II: Dang Valley-Rapti Valley (Deukhuri) Road Tunnel
Number of Alignments Considered for Study: 6 Alignments
Length of Feasible Alignment: 8.61 Km (Arjun Khola-Kattike Laxmipur)
Preliminary Construction Cost: NRs. 49.21 billion (372.12 million US$)
Length of Feasible Alignment: 4.028 Km (Kharkhola-Kattike Laxmipur) Optional Alignment
Preliminary Construction Cost: NRs. 19.29 billion (145.86 million US$)
• Preparation of DPR of River Training works along Rapti River.
Stretch of River Training Design: 24.52 Km segment of Rapti River and tributaries
Structures Provided: Embankment, Launching Apron and Spur
Estimated cost of project: NRs. 58.26 billion (440.58 million)
• Preparation of DPR of Main Road of Administrative Zone
Length of Road: 2.34 Km
Width of Road: 42.95m
Number of Lanes: 6 Lane
Type of Pavement: Asphalt Concrete
Estimated cost of project: NPR. 522,709,517.32 (3,952,630.58 US$)
• Preparation of DPR of Bus Park
Total Site area: 52005.97 Sq.m
a. Terminal Building
Type of Structure : RCC
Plinth Area : 1627.44 Sq.m
Floor Area : 3740.9 Sq.m
b. Transit Bay
Type of Structure : Steel Structure
Plinth Area : 716.5 Sq.m
Floor Area : 716.5 Sq.m
C. Landscaping
Area : 19573.93 Sq.m
• Preparation of DPR of Auto Village
Total Site area: 75481.32 Sq.m
a. Bank
Type of Structure : Steel Structure
Plinth Area : 188.22 Sq.m
Floor Area : 188.22 Sq.m
b. Administration
Type of Structure : Steel Structure
Plinth Area : 188.22 Sq.m
Floor Area : 188.22 Sq.m
c. Restaurant
Type of Structure : RCC
Plinth Area : 210.48 Sq.m
Floor Area : 230.28 Sq.m
d. Spare Parts
Type of Structure : Steel Structure
Plinth Area : 1464.85 Sq.m
Floor Area : 1464.85 Sq.m
e. Body Spare
Type of Structure : Steel Structure
Plinth Area : 1207.56 Sq.m
Floor Area : 1207.56 Sq.m
f. Washing area (Bus/Car/Bike)
Type of Structure : Steel Structure
Plinth Area : 400 Sq.m/ 238.5 Sq.m/ 174 Sq/m
Floor Area : 400 Sq.m/ 238.5 Sq.m/ 174 Sq/m
g. Painting Area
Type of Structure : Steel Structure
Plinth Area : 757.74 Sq.m
Floor Area : 757.74 Sq.m
h. Total Landscaping Area : 22068.66 Sq.m
Total estimated cost of project: NPR. 811,297,333.00 (619,939,7.95 US$) (Bus Park and Auto Village)
• Preparation of DPR of Administrative as well as Residence Buildings (Ministers and Staff Quarters) with Facilities
Total Site area: 105342 Sq.m
a. Minister’s Quarter (20 numbers)
Type of Structure : RCC
No of Stories : 2
Plinth Area : 198.85 Sq.m
Floor Area : 422.14 Sq.m
b. Staff Quarter (20 numbers)
Type of Structure : RCC
No of Stories : 4
Plinth Area : 380.06 Sq.m
Floor Area : 1550.6 Sq.m
c. Community Hall (Big)
Type of Structure : Steel Structure
Plinth Area : 354 Sq.m
Floor Area : 354 Sq.m
d. Community Hall (Small)
Type of Structure : Steel Structure
Plinth Area : 122 Sq.m
Floor Area : 122 Sq.m
Estimated cost of project: NPR. 2,321,761,397.00 (17,741,365.91 US$)
• Preparation of Detailed Project Report (DPR) of Rapti River Corridor Road
• Length of Road: 41.927 Km
Width of Road: 23 m, comprising Carriage way, Footpath, Drainage, Shoulder, Median, Handrail, Green Space
Number of Lanes: 4 Lane
Type of Pavement: Asphalt Concrete
• Length of Road: 3.504 Km
Width of Road: 7 m
Number of Lanes: 2 Lane
Type of Pavement: Asphalt Concrete
Estimated cost of project: NPR. 5,203,502,099.06 (39,761,723.53 US$)